Initial Need:

After acquiring a telecommunications building in the Punak area of Tehran, Dadeh Gostar Asre Novin Company decided to convert it into a modern data center.

Key challenges included:

  • Ensuring stable cooling
  • Quiet operation
  • Optimized energy consumption
  • Limited space

The client also required a team capable of handling the complete design, equipment supply, and mechanical installation of the data center in an integrated manner.


Solution:

After carefully evaluating the technical conditions and project constraints, air-cooled scroll chillers were proposed as the best solution in terms of efficiency and ease of maintenance.

  • Compressors were installed in custom acoustic enclosures to reduce noise.
  • Downflow internal units were custom-designed to match the server room requirements.

All stages of design, equipment supply, and installation of the cooling and HVAC systems were carried out fully and in a coordinated manner by our team.


Result:

The project was successfully completed, and the HiWeb Data Center now operates with a stable, quiet, and fully automated cooling system.

Precise performance, stable server room temperatures, and high-quality execution resulted in full client satisfaction and flawless project delivery.